The most exacting engineering element of the project was ensuring that the inner and outer ring beams up in the roof were strong enough to absorb the tension loadings of the cable assemblies, and designing them to be robust enough to suspend the grid frame from tie bars connected to the roof support structure.
The tension wire grid frame was assembled on the Roundhouse floor and lifted into its final location using nine 1.5 tonne chain blocks – in a delicate operation overseen by the Slingco installation team. It took a day to lift and fix the grid into its final position at its full height of 12 metres. This was a really tricky process as the grid needed to be picked up and raised, millimetre perfect, in exactly the right position in relation to the support steelwork and pre-positioned hanger locations.
Alignment was achieved using plumb lines, probably the same methodology that the Victorians would have used!
TENSION WIRE GRID TYPE
LongWireINSTALLATION
Architect
John McAslan & PartnersMain contractor
Tolent ConstructionTheatre consultant
TPC and CharcoalblueWant to see even more? Browse our growing gallery of Cablenet installations.
See Cablenet for yourself! We'd be happy to arrange for you to visit one of our existing tension wire grid installations, accompanied by one of our specialists.
Arrange a visitWe appreciate that all venues are unique and that design requirements can also be very different, but to help estimate budget for a Cablenet tension wire grid, we've created a simple cost estimator.
Open cost estimatorOur design, development and installation processes are structured to ensure that every stage of your experience of working with Slingco is handed in an efficient and professional manner
Find out moreTo find out more, please call, email or send our enquiry form. We look forward to speaking with you.
CUSTOM DESIGN MEANS MORE FLEXIBILITY
New build or listed building, any shape or size, tailored load capacity ... schools and colleges, theatres, exhibition halls and arenas..
COMPLETE TURNKEY SERVICE
Design, manufacture, installation, inspection and certification, including liaison with third-party architects and design teams.
SOLUTIONS TO SUIT YOUR PROJECT AND BUDGET
We’ll ensure you get the cost vs. customisation balance right.
25 YEARS EXPERIENCE, INSTALLATIONS ON FOUR CONTINENTS
Unrivalled experience and support with 12-year warranty as standard.